Activity
|
Tentative Dates
|
Description
|
|
General Clearing and Grubbing
|
4/21/2008 - 7/31/2008
|
Stonebreak Rd Ext. to Western Connector to Main Access Rd, then Eastern
Connector and Cold Springs Connector
|
|
Stonebreak Road - Earthwork
|
5/19/2008 - 9/19/2008
|
Mass earthwork on
Stonebreak Road
|
|
Main Access - Earthwork
|
4/21/2008 - 9/25/2008
|
Mass earthwork will start from Rt. 67, out to Cold Springs Connector,
balancing cut/fill.
|
|
Eastern Connector & Cold Spring Road - Earthwork
|
9/26/2008 - 10/23/2008
|
Mass earthwork
|
|
Stonebreak Road - Drainage
|
5/1/2008 - 10/31/2008
|
Installing all closed
drainage and completing stormwater basins
|
|
Main Access - Drainage
|
6/1/2008 - 12/31/2008
|
Installing all closed
drainage and completing stormwater basins
|
|
Saratoga Water Services Water Line
|
5/1/2008 - 6/31/2008
|
Installing, testing and
making connections to existing water lines.
|
|
Saratoga County Water Authority - 30" Water Line
|
6/1/2008 - 11/31/2008
|
Installing, testing
water main following mass excavation
|
|
Bridges Construction
|
8/1/2008 - 10/15/2008
10/15/2008 - 12/31/2008
|
Cofferdams, Steel
Bearing Piles, Footings, Precast Arches
Cofferdams, Footings, Precast Arches, Lightweight fill
|
|
Paving
|
5/1/2009 - 8/31/2009
|
Subbase, Asphalt Base &
binder will be placed, the final slope trimming will be completed and
then the asphalt top course placed.
|
|
Wetland Mitigation Areas
|
5/26/2008 - 6/6/2008
9/15/2008 - 10/31/2008
|
excavation, grading
wetland landscape plantings
|