Project News
July 07, 2008 -
During the week of July 7,
2008, new waterline will be connected to eliminate
conflicts with existing lines that serve the Woodfield
Estates neighborhood, as well as Malta Medical Arts and
Saratoga Sports Medicine. No shutdown of service is
anticipated. Additionally it is possible the contractors
work hours will be extended to make these connections.
Residents and businesses will be notified individually
if future planned shut down of service is expected.
June 13, 2008 - The utility installation that was
scheduled for today has been moved to Monday 6/16/2008.
The contractors hours may need to be extended to
complete this installation.
June 12, 2008 - The utility installation that was
scheduled for today has been moved to Friday 6/13/2008.
The contractors hours may need to be extended to
complete this installation.
June 10, 2008 - On Thursday June 12th the
Contractors hours may need to be extended to complete a
utility installation.
May
22, 2008 -
The contractor has completed most of the clearing
needed for the Western Connector Road and the first
segment of Main Access between the Western connector and
Route 67. Tree Clearing for wetland mitigation
areas has also been completed. Excavation and
clearing operations have begun for the western segment
of Stone Break Road. Drainage system installation is
being progressed on the Eastern segment of Stone Break
Road.
© 2008 Creighton Manning Engineering, LLP 17 Computer Drive West · Albany, NY 12205 · 518-446-0396 Please send any
comments/questions regarding this site to
LFTC@cmellp.com
All images used on this website are copyrighted by Creighton Manning Engineering. Any reproduction or unauthorized usage is forbidden except with the expressed written consent of Creighton Manning Engineering,
LLP. |